SAFETY WARNINGS AND INFORMATION 

CAUTION 

KNOWLEDGE OF PROPER INSTALLATION AND SERVICE PROCEDURES IS ESSENTIAL TO THE  SAFE OPERATION AND MAINTENANCE OF KOLD-DRAFT EQUIPMENT. REFER ALL  INSTALLATION AND SERVICE WORK TO QUALIFIED TECHNICIANS.

ALWAYS DISCONNECT THE POWER SUPPLY BEFORE SERVICING THE EQUIPMENT OR WHEN  THE EQUIPMENT WILL NOT BE USED FOR A PERIOD OF TIME. SOME CIRCUITS REMAIN  ENERGIZED WHEN THE ICE MACHINE IS SWITCHED OFF.

NEVER OPERATE EQUIPMENT THAT HAS BEEN DAMAGED OR DOES NOT HAVE ALL THE  PROTECTIVE COVERS IN PLACE.

NEVER OPERATE EQUIPMENT THAT HAS BEEN ALTERED FROM THE ORIGINAL KOLD-DRAFT  SPECIFICATIONS.

SPECIAL ATTENTION SHOULD BE GIVEN TO POTENTIAL HAZARD LABELING ON THE  EQUIPMENT AND THE SIGNAL WORDS AND SYMBOLS THAT ARE USED THROUGHOUT THIS  MANUAL.

INSTRUCT ALL PERSONNEL IN THE PROPER USE OF THE EQUIPMENT.

CLEAN UP ANY SPILLAGE IMMEDIATELY.

FAILURE TO COMPLY WITH ALL KOLD-DRAFT INSTALLATION GUIDELINES MAY CAUSE  PERSONAL INJURY, EQUIPMENT OR PROPERTY DAMAGE AND MAY VOID THE PRODUCT  WARRANTY.

STACKING INSTRUCTIONS 

Remove the cabinet panels from the upper and lower ice machines.

Mount the frame spacers on the top side panel flanges of the lower ice machine frame. Position so the spacer holes are aligned with the holes in the frame (see illustration below).

For standard GB Series ice machines, position the front panel hanger on the top front rail of the lower ice machine  (see illustration below).

FRAME SPACER PLACEMENT GB SERIES AND GBX SERIES

FRONT PANEL HANGER PLACEMENT GB SERIES ONLY

For GBX Series ice machines, a front panel hanger is not used. Instead a black panel trim is placed over the top of the  lower ice machines front panel, when the front panel is mounted (see illustration below).

PANEL TRIM MOUNTING GBX SERIES ONLY

Apply the gasket provided to the top of the lower ice machine frame as shown. Place the gasket over the frame  spacers to secure them in position (see illustration below).

Position the stacking chute in the lower machine as shown. Locate on the support channels, against the partition wall.

Carefully lift the upper machine and place it on top of the lower machine and align the frames. Fasten the frames  together using the screws, washers and lock nuts provided (see illustration below).

Replace the front and back deflectors, provided with the ice machine, with the deflectors provided in the stacking kit.  Install the deflectors into the slots in the back wall and front rail. Push down on the deflectors until they engage the  stacking chute and snap in place.

Feed the bin probe from the upper machine, through one of the holes in the upper machine condensing unit pan and position in one of the holes in the lower ice machine condensing unit pan and adjust as required (illustration below).